M4 East - Environment

Environment Protection Licence

Document titleDate and revision
Environmental Protection Licence - Including premise boundary maps30 August 2018
Pollution Incident Response Plan26 February 2016
EPL Monitoring Data 
Water Discharge Monitoring ReportMarch 2019
Water Discharge Monitoring ReportFebruary 2019
Water Discharge Monitoring ReportJanuary 2019
Water Discharge Monitoring ReportDecember 2018
Water Discharge Monitoring ReportNovember 2018
Water Discharge Monitoring ReportOctober 2018
Water Discharge Monitoring ReportSeptember 2018
Water Discharge Monitoring ReportAugust 2018
Water Discharge Monitoring ReportJuly 2018
Water Discharge Monitoring ReportJune 2018
Water Discharge Monitoring ReportMay 2018
Water Discharge Monitoring ReportApril 2018
Water Discharge Monitoring ReportMarch 2018
Water Discharge Monitoring ReportFebruary 2018
Water Discharge Monitoring ReportJanuary 2018
Water Discharge Monitoring ReportDecember 2017
Water Discharge Monitoring ReportNovember 2017
Water Discharge Monitoring ReportOctober 2017
Water Discharge Monitoring ReportSeptember 2017
Water Discharge Monitoring ReportAugust 2017
Water Discharge Monitoring ReportJuly 2017
Water Discharge Monitoring ReportJune 2017
Water Discharge Monitoring ReportMay 2017
Water Discharge Monitoring ReportApril 2017
Water Discharge Monitoring ReportMarch 2017
Water Discharge Monitoring ReportFebruary 2017
Water Discharge Monitoring ReportJanuary 2017
Water Discharge Monitoring ReportDecember 2016
Water Discharge Monitoring ReportNovember 2016
Water Discharge Monitoring ReportOctober 2016
Water Discharge Monitoring ReportSeptember 2016
Water Discharge Monitoring ReportAugust 2016
Water Discharge Monitoring ReportJuly 2016
Water Discharge Monitoring ReportJune 2016
Water Discharge Monitoring ReportMay 2016
Water Discharge Monitoring ReportApril 2016

 

Department of Planning Conditions of Approval Documents

 

Document title (as per COA)Condition of approvalDate and revision
Project ApprovalA2N/A
Environmental Impact StatementA2N/A
Submissions reportA2N/A
SSI ApplicationA2N/A
Modification 1 - Application - Modify D38A2N/A
Modification 1 - Approval - Modify D38A2N/A
Modification 2 - Application - Iron Cove Creek stormwater outletsA2N/A
Modification 2 - Approval - Iron Cove Creek stormwater outletsA2N/A
Modification 3 - Application - Tree conditionA2N/A
Modification 3 - Approval - Tree conditionA2N/A
Moditification 4 - Application - Dobroyd Parade cul-de-sac and Parramatta Road kerb extension at Rogers AvenueA2N/A
Moditification 4 - Approval - Dobroyd Parade cul-de-sac and Parramatta Road kerb extension at Rogers AvenueA2N/A
Modification 5 - Application - Modify Part E conditionsA2N/A
Modification 5 - Approval - Modify Part E conditionsA2N/A
Review of Environmental Factors (REF) Utilities and Services Enabling Works January 2016A2N/A
Review of Environmental Factors - (REF) Addendum 1 - Utility and Services Enabling Works March 2016A2N/A
Review of Environmental Factors - (REF) Addendum 2 - Utility and Services Enabling Works October 2016A2N/A
Review of Environmental Factors - (REF) Geotechnical Investigations November 2015A2N/A
Review of Environmental Factors - (REF) Geotechnical Investigations August 2015A2N/A
Review of Environmental Factors - (REF) St Luke's Park Sport Facilities Works July 2015A2N/A
Revised Staging Report - April 2016A10N/A
Compliance Tracking ProgramA147 April 2016
Pre-Construction Compliance ReportA14(c)(ii)10 May 2016
Quarterly Construction Compliance Report - 23 April 2018 - 22 July 2018A14(c)(ii)10 December 2018
Quarterly Construction Compliance Report - January to April 2018A14(c)(ii)5 November 2018
Quarterly Construction Compliance Report - April to July 2017A14(c)(ii)22 January 2018
Quarterly Construction Compliance Report - July to October 2017A14(c)(ii)13 August 2018
Quarterly Construction Compliance Report - October 2017 to January 2018A14(c)(ii)9 October 2018
Quarterly Construction Compliance Report - July 2016A14(c)(ii)12 September 2016
Quarterly Construction Compliance Report - October 2016A14(c)(ii)5 May 2017
Quarterly Construction Compliance Report - January 2017A14(c)(ii)27 June 2017
Quarterly Construction Compliance Report - April 2017A14(c)(ii)24 November 2017
Tunnel Ventilation Incident Response & Traffic Management System Integration ProtocolB719 December 2018
Flood Mitigation Strategy - Project Wide - Permanent Works Final DesignB1423 September 2016
Flood Mitigation Strategy - Wattle Street - Temporary Works Final DesignB1415 June 2017
Flood Mitigation Strategy - Parramatta Road - Temporary Works Final DesignB1415 June 2017
Flood Mitigation Strategy - Concord Road - Temporary Works Final DesignB1415 June 2017
Flood Mitigation Strategy - Homebush (Zone 20) - Temporary WorksB1414 April 2016
Groundwater Modelling ReportB1723 September 2016
Water Quality Monitoring Program - OperationalB18Revision 4 - 17 January 2019
Water Quality Plan and Monitoring ProgramB18Revision 3 - 21 April 2017
Stormwater Drainage Report - Project Wide - Temporary and Permanent WorksB2019 August 2016
Water Reuse StrategyB2124 June 2016
Heritage Salvage ReportB24July 2016
Heritage Interpretation PlanB32March 2019
Pre-construction Asset Condition Survey - Ashfield CouncilB432 May 2016
Pre-construction Asset Condition Survey - City of Canada BayB432 May 2016
Pre-construction Asset Condition Survey - Strathfield CouncilB432 May 2016
Urban Design & Landscape Plan - Section 1 - IntroductionB45;B4613 November 2018
Urban Design & Landscape Plan - Section 2 - GeneralB45;B4613 November 2018
Urban Design & Landscape Plan - Section 3 - Tunnel Portals & Dive StructuresB45;B4613 November 2018
Urban Design & Landscape Plan - Section 4 - TunnelB45;B4613 November 2018
Urban Design & Landscape Plan - Section 5 - Tunnel Services Buildings B45;B4613 November 2018
Urban Design & Landscape Plan - Section 6 - BridgesB45;B4613 November 2018
Urban Design & Landscape Plan - Section 7 - Retaining WallsB45;B4613 November 2018
Urban Design & Landscape Plan - Section 8 - Noise WallsB45;B4613 November 2018
Urban Design & Landscape Plan - Section 9 - Landscape DesignB45;B4613 November 2018
Urban Design & Landscape Plan - Section 10 - Landscape MaintenanceB45;B4613 November 2018
Urban Design & Landscape Plan - Section 11 - Operational LightingB45;B4613 November 2018
Urban Design & Landscape Plan - Section 12 - Tolling InfrastructureB45;B4613 November 2018
Urban Design & Landscape Plan - Section 13 - Site Wide VMSB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix A - Access & Connectivity Management Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix B - Concord Road Interchange Urban Design & Landscape Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix C - Wattle Street Interchange Urban Design & Landscape Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix D - Arnott's Reserve Urban Design & Landscape Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix E - Cintra Park Precinct Urban Design & Landscape Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix F - Noise Barrier Location and Design Sub - PlanB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix G - Consultation RecordB45;B4613 November 2018
Urban Design & Landscape Plan - Appendix H - Visual Screening AssessmentB45;B4613 November 2018
Urban Design and Landscape Plan Addendum 1 - The SprinterB45; B4620 June 2018
Community Communications StrategyC127 September 2018
Land Use SurveyD10N/A

WestConnex M4 East Project - Haberfield Conservation Area Archival Recording Research Report

The archival recordings for houses and streetscapes (photographic and video) are available upon request by emailing:
info@westconnex.com.au with the subject heading - M4 East archival recordings for houses and streetscapes.

D35;D36November 2018

WestConnex M4 East Project - Powell's Estate Conservation Area Archival Recording Research Report

The archival recordings for houses and streetscapes (photographic and video) are available upon request be emailing:
info@westconnex.com.au with the subject heading - M4 East archival recordings for houses and streetscapes.

D35;D36November 2018
Archaeological Research Design and Excavation MethodologyD37March 2016
Excavation Report: Historical Archaeological Investigations - Volume 1
Excavation Report: Historical Archaeological Investigations - Volume 2
D39March 2019
Spoil Management PlanD4613 December 2016
Ancillary Facilities Management PlanD51Revision 22 - 31 August 2018
SSAFMP - C11 Dobroyd UtilitiesD53Revision 17 August 2017
SSAFMP - C12 Traffic Control CentreD53Revision 17 - August 2017
SSAFMP - C13 Five Dock Motor RegistryD53Revision 17 - August 2017
SSAFMP - C14 Queen Lane SiteD53Revision 17 - August 2017
Construction Environmental Management PlanD56Revision 4 - 25 October 2017
Construction Waste and Resource Management PlanD56Revision 1 - 23 March 2016
Construction Traffic and Access Management PlanD57(a)Revision 21 - 18 February 2019
Construction Noise and Vibration Management PlanD57(b)9 June 2017
Construction Heritage Management PlanD57(c)2 February 2017
Construction Flora and Fauna Management PlanD57(d)Revision 4 - 6 December 2017
Construction Air Quality Management PlanD57(e)Revision 4 - 6 December 2017
Construction Soil and Water Management PlanD57(f)Revision 8 - 28 March 2018
Acid Sulfate Soils Management PlanD57(f)(v)Revision 7 - 27 March 2018
Ambient Air Quality Goal ProtocolE1019 December 2018
Monthly Ambient Air Quality and Weather Monitoring ReportsE21

January 2018
February 2018
March 2018April 2018

WestConnex M4 East - Operational Noise and Vibration Review
Annexure E - Detailed Traffic Noise Modelling Results
Annexure G - Receivers Requiring At - Property Treatment

E33September 2018